Wall-to-Wall Mezzanine
This month’s winner is (1 of 3) 60′ x 100′ mezzanines shown during installation for the US Army. Each mezzanines took about 2 weeks to install, and included 2 sets of internal stair systems and required installation of 2 roll up doors in the existing structure. Each mezzanine also came equipped with a lift gate on either end to allow pallets to be fork lifted onto the deck.
The mezzanine(s) were designed to fit the existing warehouse space exactly, requiring precise measurements and notching around the existing columns. Completed in three stages, Panel Built manufactured the mezzanine and related components, and was also responsible for the installation.